Building Flow Chart
Standard Operating Procedures — Interactive Process Documentation
Select a process to view
A
Call to Likely Client
Incoming inquiry → qualification → likely client
Available
›
B
Likely Client to Contract
Construction drawings → bid → contract
Available
›
C
Contract to Foundation Phase
Contract execution → site preparation → foundation
Available
›
D
Foundation Phase to Framing Phase
Foundation complete → staking → selections → framing begins
Available
›
E
Framing Phase to Rough In Phase
Framing → procurement → dried in → rough in begins
Available
›
F
Rough In to Exterior Finishing Phase
Walk-through → rough-ins → inspections → insulation → exterior
Available
›
G
Exterior Finishing to Interior Finishing
Porch → stone → siding → grade → surveys → interior begins
Available
›
H
Interior Finishing to Home Delivery
Interior complete → punch out → delivery
Coming soon
I
Home Delivery to Complete
Delivery → final walkthrough → project close
Coming soon
J
Change Order
Request → pricing → approval → signed → executed
Available
›
K
Office Manager Duties
Daily administrative processes
Coming soon
L
Internal Call Process
Internal call routing and handling
Coming soon
M
VDOT Process
Call VDOT → paperwork → site walk → drawing → permit
Available
›
Nested & Sub-Processes
MU
Miss Utility Process
Confirm dig → call 811 → markings confirmed
Available
›
LD
Land Disturbance Application
Fill form → submit to county → follow up → filed
Available
›
SS
Sign on Site Process
Rural or subdivision → install → photograph
Available
›
CL
Clear Lot Process
Land disturbance approval → Miss Utility → excavator
Available
›
HD
Health Dept — Well & Septic
Public check → soil test → perc test → approval
Available
›
PC
Plans to County / City
Checklist → deliver packet → county approval
Available
›